Party Barn Master Chronology
Contact info: Matt

This section is the original Partybarn page before I decided to break it down to smaller chunks. It spans from the beginning up through the install of the sub-woofer and covers all of the early work that was completed. Refer to the “Current” page for up to date information...







Shortly after moving "out to the country" in 2004 I had a large building constructed (on the left) ostensibly as a workshop and for storage (cost: $14k).  I quickly found it was too hot in the summer and too cold in the winter.  Considering the volume of the building, heating and cooling would be a challenge.  I opted to simply have another, smaller, shop built (pre-insulated) to use for my workshop (on the right).  And slowly begin the arduous task of a massive make over of building #1 in September of 2006.   When completed, this building (22x50x14ft walls) will house a 300sqf gym and an 1100sqf theater/game room (800sqf with a 300sqf loft).  This place will bring new meaning to a "Home Theater"!  It will have a 17' screen coupled with a 1080p  video projector (controlled from the loft area).  Downstairs will have a bar area along with seating and various "fun" things to be added later (such as a pool table/air hockey, dart boards, a universal video game machine, etc)  Total cost when completed will be around $35K to $40K.  After completion of the main building, a bathroom area will be added on to the Gym area, and will contain a 3/4 bathroom (toilet, sink, shower, closet, maybe a urinal) and will have a dedicated septic. 

Stages: (Italics denotes completed)

01) SEP 06 to MAR 07 Complete Gym area
02) MAR 07 Insulate lower north wall and OSB
03) APR 07 build ramp frame work and lay floor
04) APR & OCT 07 Insulate and cover ceiling on main floor
05) AUG 07 Insulate lower south wall and OSB
06) SEP 07 Build catwalk for A/C access
07) SEP 07 Install A/C units
08) MAR 07 Complete ramp storage
09) FEB 08 Move crap from loft into ramp storage
10) JAN 08 Insulate west wall top to bottom and OSB
11) APR 08 Build a removable cover for the roll up door
12) FEB 08 Insulate and OSB the high sides of the north and south walls
13) SEP 08 Frame in loft area, install wiring and lighting
14) SEP 08 Insulate and OSB loft area
15) SEP 08 Insulate and cover ceiling in loft area
16) OCT 08 Install fire escape in loft area on north wall
17) OCT 08 Build enclosure for air circulation blower in loft area and run ductwork
18) Build Bar area under catwalk
19) Loft done SEP 08  - Downstairs Done APR 08
20) Install all conduit, wiring, plugs and lighting externally on walls
21) Install heating system (don't know on this one yet – propane?) > 30,000 btu heater purchased, gas line run, still need final set up however...
22) Purchase / install 16'  projector screen on west wall
23) Build computer control station in loft and install / install projector - Rackmount computer enclosures purchased Feb 08
24) Build movable wall section to have option of isolating loft > I don't think so Tim...
25) Have all floor area carpeted with a low cut dark carpet or dark InOut carpet
26) Install surround sound system
27) Install acoustic tiles in strategic areas on walls to help the sound system out a little
28) Populate with tables, chairs, and fun stuff
29) Take a vacation > done
30) Start on the whole bathroom addition thingy for steps 31 to 40! < the septic is now in, waiting for time to build the bathroom now...


 

Here are some conceptualizations:


dimensions in feet

 

 

Let the games begin!

 

MARCH 2007

The first step is to prep a wall for "The Ramp".  The Ramp will be used to access the second floor as opposed to stairs to help instill a Movie Theater ambiance.  There will also be storage under the ramp.

Installed 1x4 slats

Insulate

Add some OSB

Set my first support after determining the angle

Begin the ramp!

Consult with the Supervisor

Lay the plywood

April 2007

Got some insulation done on the dreaded ceiling.  I built a wylie-coyote-style thingy out of the old set of steps I had.  It's working good for reaching high places!

After getting the support slats installed, I started weaving in the insulation:

I put up a couple pieces of press board that serve as my "tiles" to see how well it holds (so far so good btw):

...and on to something more fun for now...

 

Aug / Sep 2007

THE CATWALK

I WAS going to have a 4 ton A/C unit installed for cooling.  But for $4000, I decided to investigate an alternative.  I ended up getting 3 large window units.  Each one has a 1000sqf capacity.  3 should cool things down nicely.  The only problem is they need to be high off the ground to be most effective.  So what I need is a Catwalk for easy access to 2 of the 3 units.  The other unit will be in the loft area - so it's good to go.  I'll have about $1200 into the units+catwalk.  Much better than $4000 me thinks.

First I picked up about $200 in steel from a local supplier:

And made 3 of these:

Set in place:

Add some cable supports (like a suspension bridge!)

And then welded on a railing:

Next I installed the floor (about 32" wide) and primered it all black:

It turned out to be solid as a rock!  Very sturdy.  I like that it has no floor support to get in the way.

SEP 2007

Got some work done on the under-ramp storage.

Before I started:

Now:

SEP 2007

Got the A/C units installed:

There are 3 all together.  The volume of the Party Barn is about the same as a 2200sqf house.  Each of the 3 units can cool 1000sqf, so three ought to do well.  This past summer, with our homes central air off line - we cooled most of our house (1700sqf) with just one of these!  I'm quite sure 3 will be sufficient.

OCT 2007

Got much more done on the ceiling.  Finished putting the "tiles" up over the main floor.  Really a LOT of work lifting that stuff over my head!

NOV 2007

Ceiling finished!

...now getting started on the back wall...

         

The inspector examines some materials

JAN / FEB 08

"...miles and miles of OSB..."
                           - M Westfall, 2008, while removing splinters from hands...

;-)

West wall OSB and insulation complete

Next, got the south wall done as well

Ah, the meaning of "Cat Walk" at last...

APR 08

After getting some odds and ends done, I decided to paint the downstairs area before starting on the loft area:

The whole point in painting it all flat black is to keep reflectivity down.  Well, it works.  It was tough to get good pictures...

(still awaiting me to build a sliding door to cover/insulate the roll up door...)

Got the front wall OSB'd (the insulation has been done for a year - it was a quick and easy job) - and then painted the door.

Next, I built the rolling/sliding door to cover/insulate the 8' rollup door.  Here's completed pictures:

This is the completely OPEN condition: outer door up, and inner door open (hard to see!)

...this will allow me to still get big stuff in and out if need be...both doors will normally be closed and sealed.

...with the outer door down and inner door still open (slid to the left of the picture):

...both doors closed:

...the door rolls on a track of angle iron:

It's WAY dark in here now! Yikes!

 

JUN 08

I ran 160 feet of 6/3 (50 amp) wiring as well as Cat5e, coax and a water line out to the building (upgrading from its 30 amp line).  Two 30 amp line split from the Gym breaker box will supply power for the 3 AC units and the remaining power needs of the Partybarn (lighting, AV equipment, computers, icemaker, fridge, etc).  Partybarn computers will have net access via the cat5e connection from the house.  Satellite TV will be through the coax.
 
Downstairs lighting has begun.  A custom control box for lighting and other future functions is mostly complete.  The loft area framing is now half complete as well as routing all the wiring.

Some AC unit shots:

 

The control box (currently has 9 dimmers installed)

The loft area as of now:

 

...and downstairs lighting:

 


(hard to see because of all the darn black paint!)

We've hit the mid 90's outside and despite the insulation not being complete - the 3 AC units can turn the place into a meat locker!

JUN 08

More OSB done upstairs.  The final wall section will be completed after the fire escape door is installed.  More conduit and wiring run as well as a new junction box.  The 3 new lights for upstairs installed.


I connected the control box to test it out.  It works just fine.

Roscoe inspects some wiring...

Here's one of the rack mount cases that will be used for the A/V computer system

JUN 25 08

Before I can build the control desk in the loft, I needed to build the computer cabinet - so that means more welding!  woohoo!

The dimensions are:  24" deep, 20"wide and 30" tall (with rollers about 33" tall).

...right after cutting and welding:

...painted:

...install casters:

...cut (broke) some plexiglass to fit and drilled:

...painted back side:

...installed top / sides and computers:

...I still need to put a bottom of some sort on.  Underneath will house two back-up power supplies.

 

SEP 1 08

I finally got started on the control desk.  The desk will sit on the edge of the loft overlooking the rest of the building.  It will have associated computer hardware (monitors, keyboards, etc) as well as the sound system components.  Next to the desk is will the above mentioned rack will set.

I had some interesting restrictions/requirements in the design.  First, I wanted to only use materials I already had on hand.  Next, the weight of the desk needed to distribute it's weight to the floor and to both ends (to avoid any clutter underneath.  Hence the use of the heavy 4" C purlins (kind like a C channel) to keep things rigid.  When done, it can be screwed down to the wood floor and provide plenty of support.

I built the framework in the shop.

 

 

...installed

SEP 15 08

I ended up installing a pre-fab top.  It was simply the cheaper route and will work just fine.

Cut the hole for the control box and got it installed...

I opted for a three in one switch.  The first one on the left turns all the dimmers/lights off.  The second one will control plugs that will be mounted on the top rear of the desk.  The third will be for future use...

 

I also did some miscellaneous trim stuff.  The peak of the ceiling needed a custom cut piece, so that's done now.

Next, I started on the upstairs storage room.  It's in one of the corners where the ceiling is quite low - good for storage.

...put the shelves in...

It's all ready to have some walls put on now...


SEP 19 08

...got the walls put on today along with some trim pieces...

OCT 06 08

I got the fire escape door built and mounted.  This door had to be custom made since 5' tall doors seem to be scarce.  heh heh
It wouldn't make much of a door for normal use - but is better than nothing in case of fire!

...painted...


(I also got this last wall insulated and osb'd)


Watch that first step!


(I still need to install a latch and a seal...)

I made the door for the upstairs storage too:

Next up: build a small closet to house a blower for air recirculation:


(5000 cfm blower from an evaporative cooler...)

OCT 07 08

Major work done on blower room:


framework built, blower mounted (yes it's removable if need be)

The way this is going to work is, the blower will depressurize the closet it's in.  A duct running to the peak is the only route for air to go in.  The air is sucked in from the peak through a filter and then pumped back out to an adjacent duct.  From there it will be routed down to the main floor.  This way, warm air from the top will be constantly pumped down to the floor.  This will help equalize the temperature throughout the building.

duct work:

...where the filter will go:

OCT 8 08

Got the closet walls/door on and started on the duct work that will channel down to the floor:

I tested the blower out.  After oiling the bearings, it seems to work just fine, good air flow.  I need to mount a switch for on/off and one for low/high...

13 OCT 08

Pen got the upstairs cleaned up and I got it ready for paint.

masked...

The supervisor doing what they do best!

...and the painting is done!

It really turned out nice!

15 OCT 08

I got the upstairs wired.  Conduit run, lighting in the closet, power to the blower.  Also, the wiring started for downstairs:

I'll be getting the control desk it's own isolated power also...

OCT 21 - 22, 08

The Bar.

Some specs:

Table height: 42"
Length: 12'
Depth: 24" + 6" drink rail
Knee space: 8"

 

I did some conceptualizations of what I want the wet bar to look like:


basic frame


add some plywood


a hardwood plywood top


add oak planks


finished off with brass accessories and fancy lighting

 

...the actual progress today:


modified to have a drink rail


stained to preserve

OCT 23 08

I went to Lowes today and stumbled onto a good deal:

$35 a bundle for interlocking (tongue and groove) oak planks.  What a deal!  More than enough to do the top.

Some of it laid out:

With all the different looking shades and grain - this is really going to turn out nice.  I can't wait to be able to stain this and see!

OCT 28 08

Today I spent attaching the bar surface.  In most cases the planks are glued and screwed.  I used clamps each step of the way to hold things tight until the screws were in.  I wasn't able to use screws on the last row - so it is heavily glued and clamped, I'll pull the clamps tomorrow.


(I'll cut this end flush tomorrow)


...still need this last end piece glued and clamped tomorrow...

Next (for the top) I'll get an edge border made around the front and sides.  After that, do some belt sanding to make it completely uniform.  When I laid the pieces, I tried to put the most dissimilar pieces together to have the max impact when it's stained.

Today I also got some rope lighting ordered:

150 ft for about $70 from this place: http://www.1000bulbs.com

I think it will work best to conform with my conceptualization. 


I also found a brass place for the foot rest I want:

$280 for the kit from: http://www.markstaar.com/

HALLOWEEN 2008

Using my belt sander, I sanded half the bar surface (40grit, then 80grit, then 120grit)
It's turning out pretty nice!  I'm letting the glue dry on the other end before sanding the rest.  I can see I will need some wood putty for some hair line cracks here and there...

shweet!

NOV 3 08

Got some work done on the drink rail today.

...I'll let this dry overnight...

 

NOV 4 to 6 08

I've gotten quite far now.  After the drink rail, I put the base boards on (and at $22 a board I NEED a drink!)

Roscoe supervises

After a ton of sanding and some router work, I'm ready to stain.
 


wow!

Done!

And today, I popped on the first row of rope lighting.

After the lighting is done, I'll be varnishing (polyurethane) it all and adding finishing trim pieces.

NOV 11 08

OK - the lighting is done and WOW!


this is where the controls will go (OR a nice shot of some Star Trek plasma couplings - heh heh)

I also installed some mini spot underneath

The controls:

sealer and polyurethane is next...

NOV 12 & 13 08

Got some sealing / poly done

the top has 2 coats of sealer, sanded, 3 coats of polyurethane. 
It's really hard to get a consistent coat (I've done 2 coats sprayed and 1 brushed)
I'll probably hit it with one more spray coat since that gives the best surface...

Hmm, similar to this I guess (needs a footrest):

 

I'll let this stuff dry a good 24hrs...

NOV 18 - 19 08

Built some lockable storage under the bar (still need to post the pictures - oops), and I used left over oak from the bar for mirror frames and a bottle shelf.


I positioned the mirrors / shelf like this - I want bottles on the shelf to be completely reflected


these are 36" x 24" x 1/4" thick - they fit the "groove" part of the boards just right


the mirrors are offset to the left - eventually I want a flatscreen mounted to the right of them
the flatscreen would show the same as the main screen - so you can sit at the bar without turning
SPOILED!

FEB 11, 2009

Had the carpet installed today.  Looks GREAT!!  Last week I tiled around the bar (where stools will be).  PICTURES! :

It's all really coming together.

FEB 15 2009

Some current pictures now that the sound equipment is in:

 

 

more to come...

 

BACK TO MAIN PAGE